Eye on California employment: The current dispute over high-speed rail job projections
By: Michael Bernick
January 06, 2012
   
   
Over the past two weeks, the San Jose Mercury News has raised new questions regarding the job projections associated with high speed rail in California (here and here). It's a good idea to define terms, to get clear on how jobs are counted.

Job projections are undertaken for most major infrastructure projects in California and the United States, generally utilizing input-output models intended to capture job impacts throughout industries. Despite the complex modeling, the projections are more art than science.

Recently, I reviewed ten projections associated with a range of infrastructure investments in California and the United States. The projections varied widely in the number and types of job years estimated for each $1 billion spent in investment. Some of this variance was due to the different types of infrastructure (water, transit, highway), and some was due to whether the jobs were in the region, state or nation. Yet even controlling for these factors, the estimates for direct construction jobs, indirect jobs (i.e. suppliers) and induced jobs (jobs created as project expenditures spread throughout the economy) yielded varied estimates for job years per dollar spent.

In its business plan, the California High Speed Rail Authority (CHSRA) estimates that the high speed rail construction will generate 6,600 construction job years for each $1 billion spent. This falls roughly in the middle of the projections. Similarly, the CHSRA estimates that the project will create around 13,400 indirect and induced job years per $1 billionaEUR"which falls also around the middle of projections.

The Mercury News criticizes the draft 2012 business plan for its references to creating hundreds of thousands of jobs, rather than "job years". In the introduction to the job discussion in Chapter 10, the business plan does refer to "job years" and define the term: full time employment over a single year. "Job years" is the correct standard, as it avoids over counting workers who may work one or two days on a project. However, at several places in the business plan and accompanying fact sheet, the CHSRA does use the shorthand of "jobs". This needs to be cleaned up for the final draft, as it can create confusion about the number employed at any one time.

Using the estimate of 6,600 construction job years per $1 billion, the Central Valley Initial Operating Section (IOS), priced at $5.8 billion, will create roughly 38,280 job years for construction-related direct employment. As the IOS will be built over a 5-year period, the number of workers employed at any time will fluctuate as the works ramps up and down. On average, using the Authority estimates, the IOS will be employing roughly 7,000 workers at any one time.

This employment will by no means solve California's 11.3% current unemployment rate. However, I have two observations to make about the employment impact of the IOS.

First, the number of these construction jobs dwarfs the job count on all other highway and transit projects in California. Most of our highway and transit projects, even the larger ones, generate less than a hundred workers at any time; only a few projects even reach over a hundred workers at any time. High speed rail will generate more construction jobs than the current highway and transit projects in the Central Valley and nearby areas combined. The impacts will be greatest as the jobs can be targeted at construction workers in the Central Valley, where building trades unemployment has been more than 25%-30% for the past few years.

Second, even more than the direct employment, if the CHRSA's small business plan currently under consideration is properly structured, the Central Valley economy will benefit from developing an expertise in high speed rail construction. The Central Valley segment is the first segment to be built in the United States. Businesses, including environmental, design, and construction management, that work on this first segment will be positioned for work on other segments in California and throughout the country, possibly the world.

The Mercury News is correct that the project stands or falls on criteria beyond employment. The main decisions should be made on the project's role in meeting transportation mobility and environmental policies. The CHSRA's plan does correctly set out its projections in "job years", though greater precision in language is warranted in the final version.